spot_img

BME honoured again with...

With its safety focus entrenched as a key aspect of overall operational excellence,...

TOMRA Mining to provide...

Koura has once again chosen TOMRA Mining to support its operations at the...

Why pump rental makes...

In an environment where capital is not always available, renting dewatering pumps from...

Optimising conveyor efficiency with...

Effective conveyor belt tracking is essential for maintaining operational efficiency and preventing issues...
HomePRESS RELEASEAccelerated Bridge Construction:...

Accelerated Bridge Construction: Definition and Benefits

What Is Accelerated Bridge Construction?
Accelerated bridge construction (ABC), is a quicker and smarter way to build and install bridges by minimizing the disruption caused by road and waterway closures.

With an estimated quarter of the bridges in the United States in need of repair or replacement, it’s no surprise the ABC approach to bridge construction is becoming more widely adopted.

In addition to time-saving, accelerated bridge construction provides other benefits too. Compared to traditional methods, ABC uses more effective planning, design, and procurement methods. The result of this is improved public and worker safety, and bridges that last for longer without the need for maintenance.

The Main Aspects of Accelerated Bridge Construction

Source: Accelerated Bridge Construction Technologies: FHAW Every day Counts Initiative
A simple way to understand ABC is to split the activities into the five main aspects as shown in the United States FHWA (Federal Highway Administration) Every Day Counts Initiative:

Foundation and Wall Elements – Simplified continuous process piles cast-In-place (ACIP) piles, Geosynthetic Reinforced Soil Integrated Bridge System, Prefabricated Pier Cofferdams, Rapid Embankment Construction.
Fast Track Contracting – Different models of contracting that combine the parties involved. For example, Design and Build – with early contractor input into design decisions.
PBES (Prefabricated Bridge Elements and Systems) – Fabricating elements in a controlled environment off site for assembly at the bridge location. Described in more detail later in this article.
Structure Placement Methods – Transporting and moving the elements into position.
Why Accelerated Bridge Construction is Faster
ABC involves manufacturing large components and modules offsite and transporting them to the bridge location for quick installation. Depending upon the project and type of bridge, the installation can typically last just a few hours or 2 to 3 days.

By comparison, conventional bridge construction methods do not center around the objective of reducing construction time. Instead, they rely on sequential time-consuming stages, such as casting concrete in place, and adding reinforcing steel – often held up by weather conditions.

Measuring the Effectiveness of Accelerated Bridge Construction
There are two main metrics used to measure time in accelerated bridge construction projects:

Onsite Construction Time. From when the first contractor makes alterations to the job site until all the construction-related equipment is removed. Includes materials, equipment, personnel, and traffic control.

Mobility Impact Time. The period of time when traffic flow is impacted because of the project. This is categorized using 6 tiers.

Tier 1: Traffic impacts within 1 day
Tier 2: Traffic impacts within 3 days
Tier 3: Traffic impacts within 2 weeks
Tier 4: Traffic impacts within 1 month
Tier 5: Traffic impacts within 3 months
Tier 6: Overall project schedule is significantly reduced by months to years

traffic jam bridge construction
Total project time is a metric that gets less attention than the other two. This is because all bridge projects need planning – regardless of the construction methods used. The total project time is calculated from when project planning begins until all construction work is completed.

Prefabricated Bridge Elements and Systems (PBES)
Prefabricated Bridge Elements and Systems (PBES) are the components of a bridge made either off-site or nearby. From a project management perspective, these items are not on the critical path so do not affect the construction time. Advanced design and high-performance materials used under controlled environmental conditions ensure long-term durability, high quality, and safety.

Example Prefabricated Elements Used in ABC
Deck Elements
Beam Elements
Pier Elements
Abutment and Wall Elements
Superstructure Systems – Deck and primary supporting members.
Total Bridge Systems: The entire superstructure and substructures. (Rolled/launched/slid/lifted into place).
Structure Placement Methods and Equipment
The size and weight of the elements in accelerated construction projects can be considerable. Cranes are still used for bridge construction, but there are many other types of heavy lifting technologies used – each with its own merits.

Equipment Type by Application
Strand Jacks

A strand jack has a much smaller footprint than a crane and provides greater precision. Also, a single operator can control several strand jacks synchronously via computerized control from a central location.

Strand Jacks work by lifting the load from above, which makes them especially useful when constructing a bridge over a waterway. The case study below describes how strand Jacks were used to lift 11 deck sections during the construction of the Golden Horn Metro Bridge in Istanbul.

Strand Jacks Bridge Case Study
Strand Jack Product Specs
Jack Up Systems
A Jack Up System uses hydraulics to lift incrementally from below the load. A typical setup includes four or more jack-up units, one positioned at each corner the load. Enerpac Jack-Up units contain four hydraulic cylinders in each unit to lift and stack strong steel boxes. These automatically slide into position to support the load and form lifting towers. Lifting speed depends upon the model chosen, but this is generally between 5 and 20 feet per hour. A Jack Up System is ideal in situations where overhead cables prevent lifting from above.

The following case study describes how a Jack Up System played a key part during the construction of helped the Fore River Bridge in Massachusetts, US. Using an Enerpac Jack Up System helped to ensure minimal disruption to vehicle and boat traffic.

Jack Up System Case Study
Jack Up Systems Specs
Self-Propelled Modular Transporters (SPMTs)
These are high-capacity and highly maneuverable transport trailers. Unlike trucks, SPMTs are self-propelled from the onboard hydraulic power pack. They are ‘modular’ because two more can be connected to transport longer loads.

The example below shows a bridge deck being moved into position using Enerpac Cube Jacks mounted onto an SPMT.

SPMT (Self Propelled Modular Transporter) with Enerpac SCJ100 Cube Jacks for positioning a bridge deck.
Horizontal Skidding Systems
Skidding Systems provide the ability to slide large segments by minimizing the force needed to push bridge segments into place. They work using push-pull hydraulic cylinders and pre-constructed tracks covered with low friction PTFE-coated pads.

A good example showing a skidding system used for Accelerated Bridge Construction is when a new bridge structure over the Holbrook Canal was built adjacent to the original bridge. It was temporarily used as a detour while the deficient bridge was demolished and later slid into the position using a skidding system.

Get notified whenever we post something new!

Continue reading

BME honoured again with CAIA safety award

With its safety focus entrenched as a key aspect of overall operational excellence, BME has been recognised as a leading force in safety at this year’s annual Chemical and Allied Industries Association (CAIA) Responsible Care® awards. Held in Sandton in...

TOMRA Mining to provide XRT sorting technology for Koura’s Las Cuevas operation, the world’s largest fluorspar mine

Koura has once again chosen TOMRA Mining to support its operations at the Las Cuevas fluorspar mine in Mexico, convinced by the superior performance of TOMRA XRT sorters in removing waste from their feed. This choice also reflects Koura’s...

Why pump rental makes sense for quarries and mines

In an environment where capital is not always available, renting dewatering pumps from IPR (Integrated Pump Rental) allows cash-strapped quarries and mines to save money, access the newest technology and benefit from the unmatched flexibility and scalability. Due to their...
spot_img