HomePRESS RELEASEInnovative removal of...

Innovative removal of raisebore head helps keep Platreef on track

At the end of the raiseboring – or reaming – stage for Shaft 2 of Ivanplats’ Platreef project in South Africa’s Limpopo province, an innovative solution was called for to promptly remove the reaming head and avoid costly standing time.

Fred Durand, Senior Project Manager at Murray & Roberts Cementation, explains that an acceleration of the build plan at Shaft 2 had seen construction underway on the shaft’s headgear in 2024 – before the completion of raiseboring.

“When a reaming head reaches the surface at the end of a raiseboring process, we normally use a mobile crane from surface to help us dismantle the machine and to load it onto trucks for removal from site,” says Durand. “With the acceleration of the mine’s plan for Shaft 2 readiness, however, the construction of the headgear had been brought forward – so it was no longer feasible to position a crane in that area to remove the raisebore machine.”

“The kibble winder was not installed yet, so we had to engineer our way out of this situation to reduce raisebore standing time costs,” he says.

Related Articles
ERG Deploys Autonomous Trucks, AI Technology at Kazakhstan Operations in push toward mining innovation
ERG Deploys Autonomous Trucks, AI Technology at Kazakhstan Operations in push toward mining innovation
6 hours ago
Innovation solution
The solution began with a visit from one of Murray & Roberts Cementation’s rigging specialists from the company’s Bentley Park training and technical facility near Carletonville. His concept was to make use of a reeve block – or pulley block – system and winch which could be secured with limited steel work at the bank elevation.

“We prepared a proposal which described how reeve blocks could be secured to the sinking sheave wheel floor steel work by means of slings and beam clamps,” Durand continues. “We would then use an eight tonne electrical winch, secured to the bank, to operate the reeve block system.”

After the Murray & Roberts Cementation team were satisfied that the methodology would work, they conducted a rigorous risk assessment and prepared the necessary mitigation measures. The plan was then ready for the client’s consideration – leading to a green light to proceed. Personnel and equipment were soon mobilised, and the necessary medicals and inductions completed in preparation for the reamer coming to surface at the end of its 950 m journey from underground.

“Our solution worked perfectly, allowing us to strip the raisebore machine and hoist it to the bank area – to be placed onto the support bridge and moved out of the shaft headgear,” he says. “A mobile crane then lifted the machine onto the laydown area, ready for removal.”

Durand concludes that Murray & Roberts Cementation’s uncompromising approach to safe working practices ensured that this engineering solution was applied safely and efficiently within the tight timeframe. The company’s core safety values recently earned it the landmark achievement of 8 million fatality free shifts.

Get notified whenever we post something new!

Continue reading

Zambia Airways Launches Scheduled Services to Harare, Zimbabwe

Zambia Airways (2014) Limited, the national airline of the Republic of Zambia, has announced the completion of preparations to commence scheduled flight services to Harare, Zimbabwe. This new route will enhance connectivity between the two countries and is set...

Driving Trade Forward: AfCFTA, AGOA,BRICS and the Tariffs – All On The Menu At Automechanika CEO Breakfast

On Thursday, 8 May, leading figures in the automotive industry met at the Centurion Country Club for another Automechanika CEO breakfast event – “The African Connection” -, hosted by Messe Frankfurt South Africa. “As we navigate shifting trade agreements, tariffs,...

Namibia is struggling to achieve its goal of becoming a logistics hub, prompting a review of the master plan

Namibia has fallen short of its ambitious target to become a regional logistics hub by 2025, as set out in the fourth National Development Plan (NDP4). In response to this setback, a comprehensive master plan is currently under review,...
spot_img